Sugözü Power Plant Field Works

DECRIPTION: SUGÖZÜ ENERGY PLANT WASTE STORAGE AREA and NEW WATER COLLECTION POOL CONSTRUCTION WORKS TURNKEY CONSTRUCTION
EMPLOYER: İSKENDERUN ENERJİ ÜRETİM VE TİCARET A.Ş
PLACE OF WORK: YUMURTALIK / ADANA
ESTIMATED COST: 1,689,718,60 USD
START DATE: 01.08.2005
DATE OF COMPLETİON: 29.12.2005
PERIOD: 150 Days
PROJECT INFORMATION: Within the scope of the project, the first settling pool with a capacity of 2.000 m³ and a collection pool with a capacity of 23.000 m³, 30.000 m³ excavation and controlled filling, clay coating, geotextile membrane, PE-HD works, reinforced concrete works, pumping facility and various infrastructure works have been completed.